Analyses of the Flood Wave Propagation in Case of “Nedavic” Dam Breach at the Section From the Dam to the Urban Area of Konjic
Investor: EFT HE Ulog d.o.o. Kalinovik
INTRODUCTION
Hydraulic analyses, especially those considering process of flood wave propagation in emergency situations for hydro power plants (dam overflow or breach) are very important since enable interpretation of hydraulic features of extreme hazards and risk of flooding the downstream sections of watercourses....
More
Author: Admin
STUDY ON DISLOCATION AND EXTRACTION OF MATERIAL FROM THE RIVER BED
Ministry of Agriculture, Forestry and Water Management, Public Institution „Vode Srpske“, 2022
During 2022, Zavod za vodoprivredu has developed Studies for dislocation and extraction of material from the watercourses on 47 locations. Locations for the Studies on disposing river sediment are identified by Terms of Reference and selected by river basins based on following numbering:
Sava - 4 locations;
Drina - 14 locati...
More
Supervision of Works on Construction of “Usora” Pump Station, Doboj
Investor: UNDP BiH
Implementation period: 2018-2020
Based on the contract on supervision UNDPBIH-18-161-LID-ZAVODZAVODOPRIVREDU-I, of 30.08.2018 concluded between UNDP BiH and Zavod za vodoprivredu d.o.o. Bijeljina, Zavod za vodoprivredu has performed construction supervision on implemented civil, hydro-technical and electrical works on construction of “Usora” pump station, Doboj. Supervisor, has regularly follow imple...
More
Consultancy Services – Supervision of BNZ-5 Irrigation System Construction on Bijeljina Municipality Territory – Donje Crnjelovo
Investor: Ministry of Agriculture, Forestry and Water Management, Agricultural Projects Coordination Units – APCU
Supervisor: Consortium Zavod za vodoprivredu d.o.o Bijeljina and Energoprojekt Hidroinženjering a.d. Belgrade is author of the Detailed Design and provides Supervision of Works, i.e of FIDIC ENGINEER (Consultant)
Contractor: Consortium „HIGRA d.o.o. Bije...
More
Consultancy Services – Development of the Detailed Design for KOJ-5 Irrigation System in Kojčinovac, City of Bijeljina
Investor: HIGRA d.o.o. Bijeljina
Implementation: Project implemented in period 2021-2022
Preliminary Design for the area of Semberija has defined spatial units, sub-systems and positions and required profiles of transport and distributive pipelines in the area of all 24 sub-systems, including KOJ-5 as basis for consideration of development of distributive network and c...
More
Preliminary Design and Detailed Design of Waste Water Treatment Plant in Teslic
Investor: EIB-Wat-San, Teslić municipality, Higra
Expected implementation period: December 2022
Consortium Higra d.o.o. Bijeljina, Zavod za vodoprivredu d.o.o. Bijeljina and Hidrokop Banja Luka engaged in December 2019 on designing and constructing activities on the 1st phase of WWTP on turn-key principle, based on Yellow Fidic, for the Teslic municipality. This type of contract means that certain knowledg...
More
STUDY ON DISLOCATION AND EXTRACTION OF MATERIAL FROM THE RIVER BED
Ministry of Agriculture, Forestry and Water Management, Public Institution „Vode Srpske“, 2020
In 2020, Zavod za vodoprivredu has developed 2 series of Studies on dislocation and extraction of material from the river bed.
Most endangered locations of alluvial deposit on Bosna, Drina, Zalomka and Sušica rivers were identified by geodetic surveying and site visits. For the proper and detailed consideration of all hydrolo...
More
Study “Economic Impacts of Climate Changes to Hydro Power Sector in Republika Srpska – Multipurpose Hydropower System of Trebišnjica
Investor: UNDP BiH
Designers: Energoprojekt – Hidroinženjering ad. Beograd & Zavod za vodoprivredu d.o.o, Bijeljina
Time of implementation: October 2019 – June 2020
INTRODUCTION
Multipurpose system for use, organization and protection of Trebišnjica river basin – „Trebišnjica“ is one of the biggest and by configuration most complex integrated developme...
More
EXPERT OPINION FOR ACQUIRING – PROLONGING THE WATER PERMIT FOR “VIŠEGRAD” HPP FOR PERIOD 2021-2026
Investor: MH Power Utility of RS, ZP “Hidroelektrane na Drini”, Višegrad
Implementation period: 2021-2022
In period from December 2021 till February 2022, Zavod has developed “Expert opinion for acquiring – extension of water permit for Višegrad HPP’s operation in period 2021-2023” which included additional hydrological analyses (development of the new hydrological time series) for Visegr...
More
Study „Hydrological Analyses of Cerničko polje“
Investor: MH Power Utility of RS, Associated company Hydro Power Plants on Trebišnjica, Energoprojekt
–Hidroinženjering ad. Belgrade–
Time of implementation: March – June 2021
INTRODUCTION
During 2021 Contract was signed between MH Power Utility of RS, AC HPP on Trebisnjica from Trebinje and company Energoprojekt-Hidroinženjering a.d from Belgrade on development of financial and technical documentation under title “Preliminary solution o...
More
Study on Economic Impacts of Climate Changes on Energetic and Agricultural Sectors in Vrbas River Basin
Investor: United Nations Development Programme Bosnia and Herzegovina
Implementation period: July 2020- September 2021
„Study on economic impacts of climate changes to energetic and agricultural sectors in Vrbas river basin“ consists of seven particular reports pursuant to provisions defined by the Contract, Annexes and Terms of Reference.
Reports are submitted and accepted by Invest...
More
Study „Mapping Urban Areas of Bosnia and Herzegovina Under the Torrential Flood Risk and Preliminary Assessment of Protection Measures Application Based on Nature-Inspired Solutions in the Area of the City of Banja Luka and the City of Tuzla”
Investor: United Nations Development Programme, BiH
Implementation period: November 2021 - March 2022
Introduction
Numerous studies dealing with natural hazards imply terrifying statistics saying that natural hazards intensity is increasing over...
More
Study on Possibilities of Use of Trebisnjica District River Basin for the Fish Cage Farming
Investor: MH Power Utility of Republika Srpska, Associated company Hydro Power Plants on Trebisnjica Ltd, Trebinje
Period of implementation: 2021-2022
Multipurpose system for use, organization and protection against flooding of Trebisnjica river basin is one of the biggest and by configuration most complex integrated development designs in the water sector implemented in the area of South Eur...
More
Preliminary design of irrigation system on agricultural areas in Semberija, Bijeljina municipality (10.000 ha) with Pilot project BNZ-5 irrigation system in Donje Crnjelovo for the area of 500 ha
Preliminary design was prepared for development of irrigation systems for the 10.000 ha of agricultural land in Semberija. Water supply source is the existing channel network. This network abstracts water from the river and transports it to the Sava river. Beside drainage of waters which was p...
More
Training for Integrated Water Resources Management and Climate Change Adaptation in B&H
Investor: UNDP B&H
Implementation period: 2019
Consortium: Institute for Water Management (IWM), Sarajevo – Consortium Leader, Institute for Water Management (IWM), Bijeljina, and ‘Enova’ Sarajevo
The project ‘Integrated Water Resources Management and Climate Change Adaptation in Bosnia and Herzegovina’ consisted of training in three workshops. The first workshop was held in Neum, 17-19 June 2019...
More
Study - Determining Environmental Flow at Seven Profiles of the Neretva and Trebisnjica
Investor: Federal Ministry of Agriculture, Water Management and Forestry, Agency for the Adriatic Sea Basin, Republika Srpska’s Ministry of Agriculture, Forestry and Water Management, Agency for the Trebisnjica River Basin District and Croatian Waters
Implementation Period: 2014
Consortium: ‘Elektroprojekt’ Zagreb – Consortium Leader, Institute for Water Management (IWM) Bijeljina and Institute for ...
More
Preliminary and Detailed Designs
Improvement of the Left Drina Bank Between the Confluence of the Krizevica and the Confluence of the Glogovska River Including the Construction of Flood Defence Embankment
(Institute for Water Management, Bijeljina & CHT Hidropoint, Banja Luka & HEC, Banja Luka, 2020)
The hazard and risk of flooding by the Drina, Krizevica and Glogovska rivers in the project area in the municipality of Bratunac was assessed as high and extremely high according ...
More
Supervision of the Project (Emergency measures for the rehabilitation from flooding – reconstruction and extension of the flood defence system in the Republika Srpska 2016-2019 – Supervision of Phase II
TG11 - Rehabilitacija pumpnih stanica za zaštitu od poplava u Republici Srpskoj (DNP Period)
TG07- WA 108 – Nadvišenje savskog nasipa u Kozarskoj Dubici
TG17-PM949 – Sanacija ruševnih obala rijeke Velike Usore u Tesliću (DNP period)
...
More
UNDP – B&H
Study of Economic Impacts of Climate Change on the Hydropower Sector in the Republika Srpska – the Trebisnjica Multipurpose Hydropower System
(Energoprojekt – Hidroinzenjering, Belgrade & Institute for Water Management, Bijeljina, 2019-2020)
Within this study we carried out basic hydrological analyses for reference profiles of hydropower facilities (existing and planned), followed by detailed hydrological analyses of the impact of climate change in the area ...
More
Update and Innovation of the Republika Srpska’s Erosion Map
(PI 'Vode Srpske', 2006 – 2015)
A large portion of land in the Republika Srpska is affected by erosion processes of varying intensity. Prerequisites for the development of erosion are geological and geomorphological specificities, hydrological, pedological and climatological characteristics, the state of the woodland, and different ways of land use.
This project began with activities on collecting relevant data on the E...